FHS Track Reconstruction Timeline

(Due to our track reconstruction project, the FHS Track will be CLOSED from June-August, 2024)

(All dates below are estimates and subject to change due to weather, supply chain issues, etc.)

FHS Track Bond Timeline (Sinking Fund)

Fenton High School Track Reconstruction

Start Date

Track Reconstruction Activity

Bid Work

Bid Awarded to:

6/11/24

Demolition of existing track

Exterior Concrete

Albanelli Cement Contractors

6/17/24

Trench drain

Asphalt paving

Asphalt Specialists

6/24/24

Pave new track

Track Surfacing

Star Trac Enterprises

7/1/24

Track surfacing

Fencing

Motor City Fence

8/5/24

Track markings & lines